Petition updateRomsey Road – Tebourba Way Traffic Lights Petition to Southampton City Council‼️ Romsey Road / Rownhams Road Update
Jeremy MoultonSouthampton, ENG, United Kingdom
Mar 18, 2026

Local Councillors have had this update from Southern Gas Networks....

 

****************

SGN Gas main replacement – affecting Rownhams Road and Romsey Road  

We’d like to provide an update on our programme of gas main replacement work taking place in your local area. Due to unforeseen engineering challenges our programme, and its traffic management, have changed from what was originally communicated, our plans are now as follows:

📆 14th March to Week Commencing 23rd March: Rownhams Road and Romsey Road – Road Closure and Traffic Lights

Rownhams Road will remain closed. We will be working under two light heads on Romsey Road. However, please note we will be flipping the works area and the live running lane. The light head at Wimpson Lane will remain as per the current traffic management set up.

📆 Week Commencing 23rd March to 30th March: Romsey Road – Traffic Lights

Following completion of reinstatement at Romsey Road junction Rownhams Road, the team will continue along Romsey Road between the junctions of Winchester Road to Rownhams Road under lights.

📆 30th March to 10th April: Romsey Road – Directional Road Closure

After this, we will amend traffic management to a westbound directional road closure between Winchester Road and Redbridge Hill, to complete a connection.

📆 10th April to 4th May: Romsey Road – Traffic Lights

The team will continue works along Romsey Road, from the junction of Winchester Road to Ashmead Road, under lights. Please note, the four-way junction of Romsey Road and Rownhams Road will be unaffected during this phase.

📆 4th May to 29th May: Wimpson Lane – Directional Road Closure

We will have a southbound directional lane closure in place on Wimpson Lane. Northbound traffic will remain unaffected.

We understand our work can be disruptive for road users and residents; our engineers are committed to completing these works as quickly and as safely as possible. These works are essential to ensure we can continue to provide a safe and efficient gas supply to residents and wider community and avoid further disruptive gas leaks in the future. 

📞 If you need to speak to us about these works, please email our customer service team customer@sgn.co.uk or call us on 0800 912 1700, they will direct your enquiry to a member of the team for response.

We’re sorry for the inconvenience caused and thank you for your patience and understanding.