Neuigkeit zur PetitionTell PSEG to Remove the Steel Poles and Bury the Transmission Lines on Eastport Manor RoadPSEG Long Island Agrees To Bury The Lines On Eastport Manor Road

Brendan O'ReillyEastport, NY, Vereinigte Staaten

04.01.2019
PSEG Long Island announced tonight:
PSEG Long Island will underground lines that are currently on approximately 24 storm-hardened poles in Eastport, from Sunrise Highway’s south service ramp to the Eastport substation on Montauk Highway. The project is expected to be complete in 2020 following required permitting, procurement, engineering studies, other design and construction-related tasks.
This agreement resulted from meetings and discussions among LIPA, PSEG Long Island, NY State Senator Ken LaValle, NY State Assemblyman Fred Thiele, Brookhaven Town Supervisor Ed Romaine, and Southampton Town Supervisor Jay Schneiderman.