monica jordanGorum, LA, United States
Jun 12, 2025
Thank you everyone for your support!!
I spoke with DOTD this morning regarding the issues with the bridge. There are embankment issues, multiple piers are bent and additional are needed as well as scour issues (erosion around piers).
This is a 2 phase project. Phase 1 is to make a temporary repair by driving new/additional piers. The repair design is still in process; the project has a projected start date of the first week of July 2025 and hopes to be completed by the time of the start of school August 2025.
Phase 2 is to replace the bridge. It will be done one lane at a time. Projected start date is Dec 2026 and is projected to take 2 years.
I will continue to follow the project.