Hi all I got this message below from our fab local councillor Dylan Parker...the timeline for our park upgrade has been set. It should be completed by August next year. Yippee!! ☺️
Hi Lyndsey,
Please find below the the current timeline for the Coral Sea Park Playground. Like all things it may be subject to change however the current timeline is as follows:
December 2020 – Initial community consultation (Setting Objectives)
February 2021 - Concept Design and consultation
May 2021 – Design Documentation Completed
August 2021 – Playground upgrade completed
Please feel free to communicate this correspondence from me to the change.org petition signatories if you wish.
Kind Regards,
Cr Dylan Parker
Randwick City Council - Central Ward (Labor)