Actualización de la peticiónBring Fibre Broadband to cabinet 2 at East Wickham, Welling.Fibre cabinet building work scheduled to start on the 30th of November.

Steve JacksonLondon, ENG, Reino Unido
18 nov 2017
According to roadworks.org, the cabinet building works are scheduled for 30th November to 7th December.
After that Openreach will start to install the equipment.
Location: A207 Bellegrove Road, Welling, Bexley
Traffic lights, etc: Some carriageway incursionInformation for Operational Teams
Highway Authority: Bexley London Borough Council
Description:
NGA - DSLAM STREET CABINET& PCP CABINET & POWER INSTALLATION.
Excavate to lay BT ducts, Lay concrete plinth, Stand cab. Excavate to expose low voltage cable for Power Connection and lay duct.
POWER engineer to carry out inspection prior to jointing.
POWER jointing team to insert cable and execute jointing works. Reinstate, Check and clear site