Good day Folks,
Our team was very productive over the winter months and I am happy to report that our liming helicopter pad is completely constructed and ready for the liming part of our project to start. Our team now has all the rock strategically located for about 1.5 km of river restoration ready to get started. We will expect road closures soon as we usually do in the spring and as conditions start to dry up our West Branch Project on the St. Mary's will be a buzz of work for 2020. The bulk of our 1.2 million Coastal Restoration Grant will be spent this year with follow up work and more restoration for 2021.
Great job Nick and Charlie!
The picture of work done last year is just below Indian Man Brook. This is a rock sill with deflector and groynes to narrow up the river.