Petition updateNo Data Center and MARICI BESS project in the City of Industry without EIR
URGENT UPDATE: August 7 Court Hearing is taken off the calendar

Puente Hills Community Preservation AssociationROWLAND HEIGHTS, CA, United States

Aug 6, 2026
The August 7 court hearing regarding PHCPA’s CEQA lawsuit is no longer needed and has been taken off the calendar by the judge’s decision. The court has issued a tentative ruling on the demurrer, sustaining it with leave to amend.
In plain words, the court has directed us to refine specific details in our petition rather than dismissing the case. We are submitting an updated filing as permitted by the judge, and our CEQA lawsuit remains active and moving forward.
Please stay tuned as we will continue to provide updates regarding the next court hearing date. Thank you so much for your unwavering support!