Construction phases for 2023:
Phase 1 County Road 34 W - From Cameron Side Road to Malden Rd
Phase 2A County Road 27 W - From County Rd 34 W to Highway #3
Phase 2B Clark/William/Francis/Lyle Subdivision
Phase 3 Road 11 W/North Talbot - West of Cameron Side Road
Additionally, Cogeco has announced plans to run fibre to 940 homes and business in Cottam. https://windsorite.ca/2023/03/cogeco-bringing-fibre-to-cottam/?fbclid=IwAR3Gz7pLL6-cScI2Ty7MbngNMFCHqLRRTHgDQ_9d1DAj3Tb-obwd9olxzv4
The announcement by Cogeco was a surprise. Although the focus of the petition was to get Gosfield Tel to run the fibre, I think many household will be thankful to have modern internet service from either Cogeco or Gosfield.
Gosfield Tel will be holding their AGM on March 28, 2023 at the Cottam United Church. Doors Open at 6:30. It is hoped there will be more information provided at the meeting.