Petition updateSTOP ELEVATED HIGHWAY OVER SUNSET BLVD, KORANGI ROAD & KHAYABAN-E-JAMI

SEPA held an incomplete Public Hearing on August 18, 2026

Jamal MacdiKarachi, Pakistan
19 Nov 2026

 

Reply to SEPA 

The Director GeneralSindh Environmental Protection Agency (SEPA)Government of Sindh, Karachi

Subject: Karachi Port to Qayumabad Corridor Project (KPQCP) - Rejoinder to 

Proponent's Responses, Non-Disclosure of Embankment Alignment, and Request for 

Hydrological & Wetland Impact Assessment

Dear Sir,

We, the undersigned residents of DHA, Clifton, and adjoining areas, respectfully submit this rejoinder in 

response to the Proponent's replies. This submission forms part of the environmental review record.

We acknowledge mitigation commitments. However, the central issue is not whether mitigation is proposed 

but whether sufficient evidence exists to demonstrate acceptability.

BEFORE approval. We have now identified material non-disclosure in the concession documents that weren't 

placed before public hearing.

NEW MATERIAL FACT - RFP ADDENDUM III DISCLOSURE:

Sindh Government's own RFP Volume-II (Concession Agreement) contradicts public representation:

a) Page 2, Vol-II: "The main alignment turns westward again as a four-lane dual carriageway earthen 

embankment running along the Mangroves in Chinna Creek..." Last 3-4 km is therefore NOT elevated 

but earthen embankment inside Chinna Creek and mangroves. Spur link similarly on embankment until 

Oil Tanker Stand. The public was told 16.5 km elevated.

b) Page 54, Clause 4.13.4: “The Concessionaire undertakes to remove, replant, or otherwise manage any 

mangroves..." Page 110: Contractor to obtain SEPA approval “including approvals for 

removal/relocation of mangroves" AFTER award.

c) Pages 15 & 22: Hydrological studies of Chinna Creek and 50-year flood return period report will be 

carried out by Concessionaire LATER to decide

Thus, mangrove removal is pre-committed in contract, SEPA approval is treated as post-award formality, and 

embankment height itself is not yet known. No independent 2D tidal model is in the public domain. *This is an 

unlawful deferral under Reg 12.* 

Key Outstanding Issues:

1. Project Scope and Approval Status

Record unclear regarding final alignment, embankment lengths, temporary works footprint, access 

arrangements, and approval status. We request disclosure of assessed version, chainage-wise embankment vs 

viaduct, KMZ maps, RFP Addendum III Vol-II, any issued approval, applicable conditions, and confirmation 

regarding site activities to date.

2. Alternatives Assessment

Dismissal of rail and M-10 Northern Bypass without transparent comparative analysis. We request objective 

multimodal assessment: M-10 (34km existing, NHA plans 8-lane + 23km 6-lane upgrade keeps >15,000 

trucks/day outside city) + KPT-Pipri 54km rail freight (Federal Jan 2026 announcement) vs KPQC inside creek. 

Residents seek lower environmental impact solution, not opposition to freight efficiency.

3. Noise and Vibration

Barrier height alone does not demonstrate protection. Daytime/nighttime predictions for residences, schools, 

and healthcare facilities should be disclosed with evidence of achieving SEPA NEQS. Risk-based vibration 

assessment and structural condition survey required.

4. Air Quality and Human Exposure

Existing poor baseline does not answer incremental exposure. Prospective operational predictions using 

realistic traffic/meteorological assumptions required. Data inconsistencies to be corrected through lab 

documentation.

5. Hazardous Cargo Transport

Transport-specific risk assessment required for dangerous cargo on elevated corridor adjacent to communities 

and creek - accident scenarios, loss-of-containment, emergency response, evacuation constraints, containment

6. Privacy, Visual, and Amenity

Visual screening requires validation through sightline analysis using representative building heights, floor levels, 

and road geometry. The feasibility of privacy protection must be demonstrated before approval.

7. Ecological Impacts and Mangrove Protection – Clarification of Legal Status – LEGAL IMPOSSIBILITY:

Chinna Creek forms part of Karachi’s coastal wetland and mangrove environment.

Undisputed Legal Status as Protected Forest:

We now bring on record a material legal fact suppressed by Proponent:

Sindh Forest Department Notification dated 15th February 2022 issued under Section 29 of the Forest Act, 1927 

(published Dawn 17.02.2022) declares:

“In exercise of powers conferred by Section 29 of Forest Act 1927… Government of Sindh is pleased to declare 
the intertidal land (mangrove areas) of Thatta and Sujawal districts described in Schedule to be ‘Protected 
Forests’ with immediate effect. Provision of Chapter IV of said Act shall be applicable to it.”
• The notification covers 750,000 acres mapped through GIS, Schedule-1 ending at west boundary of 
Ibrahim Hydri, which includes Korangi and Phitti Creek systems on which Bundal/Buddo Islands are 
located. This notification was issued on orders of Sindh High Court.
• Earlier, 2010 Notification already declared all mangroves in Sindh as Protected Forests. Director Forest 
Operations has confirmed in Dawn Investigations: “mangroves in disputed area have been declared 
protected forest, making any cutting subject to penalties.” SFD officials after site inspection have stated 
“land in question belongs to Forest Department” in China Creek area.
Therefore, China Creek mangroves are admitted Protected Forest under Section 29.
Legal Impossibility of Forest NOC:
Under Chapter IV of Forest Act, 1927:
• Section 30: Power to reserve trees – mangroves are reserved protected tree species (World Bank 
records): ”Mangroves which are protected tree species located in Chinna Creek”.
• Section 33: In Protected Forest, the following are criminal offences punishable with up to 6 months 
imprisonment + fine: (i) clearing land, (ii) breaking up land for cultivation, (iii) quarrying stone, (iv) 
building, (v) road/embankment construction, (vi) setting fire, (vii) felling reserved trees.
• The RFP itself admits on Page 2, Vol-II: “The main alignment turns westward again as a four-lane dual 
carriageway earthen embankment running along the Mangroves in Chinna Creek…” and Page 54, 
Clause 4.13.4: ”The Concessionaire undertakes to remove, replant, or otherwise manage any 
mangroves…”
A Forest Department NOC for such removal / embankment is a legal impossibility. Forest Department cannot 
grant NOC to commit an offence under Section 33. The only legal route to allow it is de-notification under 
Section 29, which requires (i) Sindh Cabinet approval and (ii) Permission of Sindh High Court, since the 
15.02.2022 notification was issued pursuant to SHC orders in Bundal/Buddo Islands case.
No such de-notification has been disclosed. Therefore, Forest NOC cannot be issued.
Consequential Bar on SEPA Approval:
Under Sindh Environmental Protection Act, 2014, Section 17 and EIA Regulations 2014 Reg 12, SEPA cannot 
issue Environmental Approval without NOCs of relevant line departments where forest land is involved.
Since Forest NOC is legally impossible, SEPA EIA approval is also legally impossible without first obtaining SHC 
permission to de-notify Protected Forest. The Proponent’s attempt to make SEPA approval for mangrove 
removal a post-award formality (Page 110: Contractor to obtain SEPA approval including approvals for 
removal/relocation AFTER award) is an unlawful deferral under Reg 12 and amounts to pre-commitment to a 
criminal offence.
International Obligations:
(i) Ramsar Convention promotes “wise use” of ALL wetlands, not only listed sites.
(ii) Pakistan’s Ministry of Climate Change lists ratified instruments: CBD, Ramsar, CMS, 
UNCLOS, and states implementation is mandatory.
(iii) CBD is particularly relevant as mangroves provide habitat for fish, crustaceans, and birds.
(iv) World Bank documentation records KPT mangrove nursery/transplantation activities in 
Chinna Creek acknowledging protected status.
Accordingly, ESIA must be rejected until Forest Dept confirms de-notification or alternative alignment outside 
Protected Forest is proposed.
8. Embankment Footprint, Tidal Exchange and Flood Risk - Strongest Unresolved  Concern:
This is the most significant concern. ESIA and RFP refer to substantial earthen embankment construction 
WITHIN Protected Forest. ESIA Annexe II admits _”blocked channels may reduce conveyance, increase flood, 
affect tidal exchange”_ but provides NO model.
Chinna Creek is Karachi’s last natural tidal drain for Clifton/DHA and is a Protected Forest where any 
embankment is an offence under Section 33.
• Block tidal exchange (reduce flushing, increase salinity/temperature)
• Increase flood levels in Clifton, DHA, Gizri during monsoon + high tide
• Destroy natural flood buffer and carbon sink
We request calibrated, independently reviewed *Chinna Creek Wetland, Mangrove and Hydrological Impact 
Assessment* covering:
• Existing bathymetry, tidal circulation, tidal range, seasonal variation
• Freshwater/seawater interaction, salinity distribution, sediment transport
• Existing mangrove distribution and density
• Proposed pier/foundation/embankment locations, construction-phase obstructions, temporary works
• Post-project hydrodynamic modelling (MIKE21/Delft3D) for: present, with embankment, 50-yr flood + 
spring tide + 0.5m SLR + storm surge, sedimentation and maintenance failure scenarios
• Consequences for neighbouring communities, outfalls, mangrove health, fish, and aquatic organisms
Project resilience must be demonstrated through evidence, not assumed through design intention. Where 
uncertainty remains, the precautionary approach requires additional investigations rather than assuming no 
impact.
Consultation and Expert Review
Substantive consideration requires more than a response matrix. If supplementary studies, corrected 
predictions, or revised components are produced, reasonable public review opportunities must be given before 
final determination.
We request SEPA exercise powers under Environmental Assessment Regulations to obtain issue-specific expert 
review on hydrodynamics, ecology, environmental health, transport alternatives, and make findings publicly 
accessible.
Relief Requested:
1. Place this rejoinder, RFP disclosure, and all correspondence on the official review record.
2. Disclose current approval status, assessment version, KMZ maps, RFP Addendum III, and any conditions 
issued.
3. Require submission of outstanding technical information identified herein, particularly hydrodynamic 
assessment.
4. Obtain independent expert review of disputed matters.
5. Prevent any unapproved filling, mangrove disturbance, or drainage obstruction pending lawful 
determination.
6. Provide a reasonable public review period for any supplementary submissions.
7. Issue reasoned decision addressing principal objections.
8. Withhold approval until decision-critical deficiencies are resolved, particularly embankment vs 

elevated non-disclosure and missing hydrology study.

Conclusion

Residents do not oppose freight efficiency, port modernization, or economic development. Our concern is that 

such objectives must be pursued through environmentally defensible solutions supported by sufficient 

evidence, transparent alternatives analysis, and enforceable safeguards, avoiding irreversible filling of Chinna 

Creek wetland and mangrove ecosystem.

Where significant uncertainty remains concerning the project's effects on Chinna Creek, SEPA should not grant 

environmental approval until the adequacy of studies has been independently reviewed.

Yours faithfully,

For the Concerned Residents of DHA, Clifton and Adjoining Areas