Mike EdmondsonColumbus, GA, United States
Sep 3, 2016
The Bibb Center Inc. is a non-profit organization. The 501(c)3 status has been applied for. All donations are appreciated and should be sent to
The Bibb Center Inc.
Post Office 534
Fortson, Georgia 31808
Your donations are tax-deductible to the full extent allowed by Federal law. Also - if you know of persons who would be willing to date, please ask or let me know, and I will contact/go see them. The project (we figure) will cost about $7.22 million. You can donate in honor of/in memory of - please indicate that on the check or a note.
The nonprofit was established by Mike Edmondson, a local retired science teacher with the intent of purchasing and renovating the deserted Bibb Elementary school into an ISTEAM (Innovation in Science, Technology, Engineering, Arts, and Mathematics) Center. Much of the facility will be devoted to middle grades education for the county and surrounding counties, as well as K - 12 and University resource and teaching needs. Workshops and summer camps will also be an important aspect.
The center will have numbers of resources to teach the noted disciplines, Kindergarten through Grade 12. All middle grades would come for intensive exposure to STEM and STE(A)M units throughout the year.
Since we are on the Chattahoochee River (two blocks away) a floating classroom is to be established. Students would move up and down the river to the Oxbow Meadows facility, a part of Columbus State University. There will be a hydroponic greenhouse, a farmer's market, a glass-glowing studio, a state of the art auditorium and recording studio, a makerspace, collaboration areas, classrooms, an outreach program that would have college faculty and interns taking programs into the community, 3D printing for the city use, and more. (A detailed proposal is available.)
All parts of the campus will be web-enabled, wifi-connected, and broadcast-capable. The facility will have solar panels on all exposed roofing areas to help defray energy costs.
There are five phases:
Phase One - Obtain building and complete site analysis for any untoward materials (asbestos and lead paint), plus an archeological survey. The school was built in 1915 by Bibb Manufacturing for the children of its employees, and in the 1800s and before, the area was populated by Indian cultures.
Phase Two - Stabilization and roofing
Phase Three - Mechanical, electrical, plumbing, and technology plan and rough-in
Phase Four - Building reconstruction/construction
Phase Five - outfitting the facility and donation to the MCSD/CSU Partnership from the nonprofit.
Total cost to purchase, renovate, and outfit - in the neighborhood of $7.22 million. Every dollar helps!