York Station Gateway project:
* Original estimated cost: £26 million.
* Current estimated total cost: approximately £60.1 million (reported July 2026).
* Increase in cost: around £34.1 million above the original estimate (around 131% over the original budget).
* Latest increase alone: an additional £5.4 million was added because of delays and unexpected works.
* An Audit and Governance Committee report found the project had “significant weaknesses” in project management and contract management.
* The audit stated the potential overspend was not reported for around two years through the council’s monthly project reporting.
* The audit found the overspend required money to be diverted from other capital projects to complete the scheme.
* £14.5 million was diverted from the York Outer Ring Road project to help fund the Station Gateway overspend