Actualización de la peticiónHigh voltage JEA power lines coming to a view near YOU

February 13th Update from Jay King via Next Door

Stephanie MckinneyJacksonville, FL, Estados Unidos
20 feb 2019

From Jay King’s Nextdoor post:

This is just a quick update on our recent interactions with JEA pertaining to plans to build powerlines to the East and South of our community. Please see the following links for additional background on the project if you are not already familiar with it from social media (Nextdoor.com and Facebook) and First Coast News reporting.

JEA Website: https://www.jea.com/us1

Link to petition with notes from recent JEA public meeting at BSE as well as contact information for local politicians and JEA:https://www.change.org/p/bartram-springs-residents-high-vol

A special thanks to Stephanie McKinney for creating the petition.

As with any issue we encourage you to do your own research and form your own opinion and welcome any dialogue to help the community become better informed. We are simply trying to facilitate in the best interests of the community as we see it in a hope to optimize the outcome for everyone.

We have been in ongoing dialogue with JEA and our city councilman Danny Becton since last Thursday when JEA held it’s public meeting at BSE and we became aware of the issues. Our most recent conversation was with Jordan Pope last night following a city council meeting. Jordan is the Director of Government Relations for JEA. He has been very accessible and engaged ever since the meeting last Thursday. We had a frank conversation. Jordan assured us that we had the attention of the most senior people at JEA and that they were clearing schedules to focus and meet on the situation. He mentioned they were following and reading the petition online and fielding calls from concerned residents. We had previously asked that another public meeting be held with better advertising and that has been agreed to in principal. We stressed that if the intent of the meeting was to simply try to better sell us on what was already planned that would fall flat. What we wanted was a sincere partnership to explore better options for the community and a willingness to alter plans to improve outcomes. We explained the three primary concerns that we had with the project that needed to be resolved before there would be public support were:

1. Impact on property values based on the visual and audio impact the 126 foot poles and lines from the homes on the streets in the community that run along the East side of our neighborhood and that the impact could extend deeper into the community based on comps. We stressed that even thought the immediate impacts are somewhat localized within the neighborhood we are unified in support of those homeowners.
2. Concerns around health implications based on the proximity of the power lines to homes.
3. The process around how and when this was noticed to the public and the lack of sincere public engagement during the planning phase. Given the planning horizon for such projects the fact that the public meeting was held just a month before ground was planned to be broken speaks for itself. We do not want to be told about or sold on a project after plans have been made that adversely affect us, but rather we want an opportunity to weigh in and shape the outcome for everyone’s benefit. We highlighted how this did not bode well for plans to privatize JEA if this is how they went about community engagement as a branch of government. We need to know that there will be a better process going forward so that this scenario does not repeat itself with another community.

We stressed that we are reasonable people and understand that the power infrastructure needs to be improved and extended to reach new service areas but we did not want to bare the brunt of the impact when other options are available and to the extent possible the costs of such alterations and mitigations should be borne equally across all rate payers or if disproportionate then to those new customers gaining service, but not simply to us out of convenience.

So as it stands we are waiting to see the results of JEA’s work based on our concerns to date and for them to set a new date for a second public meeting.

What can you do in the meantime? The best angle we believe we have at this point is to continue to circulate and sign the petition. We also recommend adding your comments to the survey to convey your specific concerns with the plans as they stand. The more voters behind it (650 as of this post) the more compelling our cause to our elected representatives and JEA. We have about 3,000 registered voters within Bartram Springs so we still have work to do. We strongly recommend we keep calls and pressure on the Mayor’s office. He appointed the JEA Board. The city “owns” JEA. He is sensitive to issues around privatization of JEA and he is up for reelection.

Major Lenny Curry: 904-630-1776, MayorLennyCurry@coj.net

We will provide additional updates as we have them. Please continue to share the issue with your neighbors so they may get engaged as they see fit.