Petition update
Letter to the Dean JJ Hospital sent to her on 19th of May 2023
Jun 6, 2023 —
19th May, 2023
To
Dr. Pallivi,
Dean , J. J. Hospital,
St. Georges Hospital,
St. George Compound,
P D’mello Road,
Opp: GPO, Near: CST Station,
Fort,
Mumbai - 400 001.
Copy to:
1. Mr. Rahul Narwekar MLA, Speaker, Maharashtra Assembly.
2. Mr. Makarand Narwekar, Corporator, Ward, 227.
3. Dr. Vinayak Swardekar, Medical Superintendent, St. Georges Hospital.
Dear Madam,
Ref : Reconstruction of the Mortuary at St. Georges hospital.
Facts of the case:
This project was initiated by the undersigned sometime in 2017 when I had gone to collect the post mortem report of my chauffeur and discovered that besides the postmortem being conducted by a class IV employee the so called morgue consisted of a broken down shed which had no door forget having any cooling facilities .
It had one fan and one bulb that was hanging.
Since then much has happened and with the assistance of Mr Rahul Narwekar , Mr. Makarand Narwekar, Ms. Harshita Narwekar the active members of CALM and My Dream Colaba along with the signature of 98600 signatories to my petition change.org/Mumbaimorgue ( you may go online and follow the trajectory of what all has happened since the year 2017. The reconstruction of the new mortuary saw some light.
The status today:
The construction of the Ground floor is almost complete. (barring the area that is encroached) However, whether it can be put to use is a million dollar question as there is no electricity connection. We have been informed that the estimate for the electrical work is pending for approval at the DMR office.
The design for the first floor had to be redone on account of the encroachment and is also pending approval at the DMR office.
I have made over the last three days almost twenty calls. Like the game of “Passing the Parcel“, I have been referred to various different persons and different numbers.
Some of the persons I have spoken to since the last three days are listed below: Some had the courtesy to take my call, others did not. Sent messages through whatsapp giving reference. No one seems to be really inclined to take ownership of the project and desires its completion:
1. You the Dean who has asked me to put down the facts.
2. Dr. Vinayak the current Superintendent
3. Mr. Hande, Chief Engineer
4. Mr. Jangle Raosahib
5. Mrs. Gavade, electrical department
6. Mr. Mundhesir
7. Mr. Shingade, Deputy Engineer
8. Mr. Kumbhare
9. Mr. Mane
10. Mr. Shingade, DE
11. Mr. Pramod Bangosavi .
12. Dr. Khobragade
This letter is to request you to take stock of the current status and use your good offices to ensure that the project acquires the momentum it deserves.
It is already 6 years since we began this interaction perhaps you as the Dean might be able to intervene and use your good offices to propel it forward.
Thanking you.
Renu Kapoor
Mob: 9821242474
renuskapoor@gmail.com
On behalf of the members of
CALM Colaba Advance locality Management
MDC My Dream Colaba
98600 signatories to the Petition on Change.org/MumbaiMorgue
Keep fighting for people power!
Politicians and rich CEOs shouldn't make all the decisions. Today we ask you to help keep Change.org free and independent. Our job as a public benefit company is to help petitions like this one fight back and get heard. If everyone who saw this chipped in monthly we'd secure Change.org's future today. Help us hold the powerful to account. Can you spare a minute to become a member today?