Oxford City Council’s response

Oct 30, 2017 — The Westgate Shopping Centre redevelopment has not yet been fully completed – workers are still on site and there are some shops still to be completed and a lot of work around the edges of the new development.

Oxford City Council, as the city’s planning authority, insisted on bicycle parking being included in the Westgate Shopping Centre redevelopment and we are pleased that new bike racks for 1,000 bicycles will be installed as part of the development.

The provision of the bike racks for 1,000 bicycles is a requirement of the planning permission for the new Westgate Shopping Centre. The development was created followed extensive public consultation with stakeholders, including cycling groups in Oxford such as Cyclox. This consultation included the location and type of bike racks that would be installed.

Sadly, although 180 cycle spaces have been installed, the installation of the majority of the new bike racks has been delayed. Last week the Westgate Shopping Centre developer apologised for this delay, and again reassured the City Council and the public that it will install all the bike racks and meet the planning requirement. On Friday, the City Council installed 50 temporary bike racks in St Ebbes Street.

We are disappointed that the cycle parking was not fully installed prior to the shopping centre being opened, and are working with the developers to ensure that it is installed and operational as soon as possible.